1500 St-Laurent Blvd.#
Last updated: 2026-10-19 · ID: D07-12-25-0095
Summary#
OC Transpo proposes constructing a new enclosed parking garage to replace the existing outdoor parking lot that currently serves OC Transpo’s buses. This development is part of a larger plan to transition approximately 450 diesel buses to a full battery electric bus fleet by 2027.
Source:
City-provided description
and 2025-07-10 - Phase Two Environmental Site Assessment - D07-12-25-0095 (Page 1)
Status
Inactive (Notice of Decision Sent)
Inactive (Notice of Decision Sent)
Project Type
Site Plan Control
Site Plan Control
Property Type
Industrial
Industrial
Building Scale (Max.)
Based on elevation drawings. Values may be approximate. See sources for exact figures.
Low-rise · 1 storey
Location#
Select a marker to view the address.
Project Updates#
Status Updated
- Status: Inactive (Notice of Decision Sent)
Added 18 documents
- 2026-06-08 - APPROVED West Storm - D07-12-25-0095
- 2026-06-08 - APPROVED Stormwater Storage & Inlet Control Details - D07-12-25-0095
- 2026-06-08 - APPROVED South Storm & Watermain Profile - D07-12-25-0095
- 2026-06-08 - APPROVED Site Servicing Report - D07-12-25-0095
- 2026-06-08 - APPROVED Site Servicing Plan - D07-12-25-0095
- 2026-06-08 - APPROVED Site Plan Approval Report - D07-12-25-0095
- 2026-06-08 - APPROVED Site Plan - D07-12-25-0095
- 2026-06-08 - APPROVED Site Grading Plan - D07-12-25-0095
- 2026-06-08 - APPROVED Sanitary Outlet - D07-12-25-0095
- 2026-06-08 - APPROVED Roof & Elevations - D07-12-25-0095
- 2026-06-08 - APPROVED OCT North Garage Watermain Upgrades Memo - D07-12-25-0095
- 2026-06-08 - APPROVED Legend & Drawing List - D07-12-25-0095
- 2026-06-08 - APPROVED Landscape Plans - D07-12-25-0095
- 2026-06-08 - APPROVED General Notes - D07-12-25-0095
- 2026-06-08 - APPROVED Existing Conditions & Removals C004 - D07-12-25-0095
- 2026-06-08 - APPROVED Existing Conditions & Removals C003 - D07-12-25-0095
- 2026-06-08 - APPROVED Erosion & Sediment Control Plan - D07-12-25-0095
- 2026-06-08 - APPROVED East Storm Profile - D07-12-25-0095
Added height and 22 documents
- 2026-03-27 - Zoning Map - D07-12-25-0095
- 2026-03-27 - West Storm Profile - D07-12-25-0095
- 2026-03-27 - Tree Preservation & Landscape Plan - D07-12-25-0095
- 2026-03-27 - Stormwater Storage & Inlet Control Details - D07-12-25-0095
- 2026-03-27 - Storm Sewer Design Sheet & Engineering Drawing - D07-12-25-0095
- 2026-03-27 - Standard Details OPSD - D07-12-25-0095
- 2026-03-27 - South Storm & Watermain Profile - D07-12-25-0095
- 2026-03-27 - Site Servicing Report - D07-12-25-0095
- 2026-03-27 - Site Servicing Plan - D07-12-25-0095
- 2026-03-27 - Site Grading Plan - D07-12-25-0095
- 2026-03-27 - Sanitary Outlet - D07-12-25-0095
- 2026-03-27 - Pre Development Drainage Areas - D07-12-25-0095
- 2026-03-27 - Post Development Drainage Areas - D07-12-25-0095
- 2026-03-27 - Legend & Drawing List - D07-12-25-0095
- 2026-03-27 - General Notes - D07-12-25-0095
- 2026-03-27 - Existing Conditions & Removals C004 - D07-12-25-0095
- 2026-03-27 - Existing Conditions & Removals C003 - D07-12-25-0095
- 2026-03-27 - Erosion & Sediment Control Plan - D07-12-25-0095
- 2026-03-27 - Environmental Compliance Approval Application - D07-12-25-0095
- 2026-03-27 - Engineering Plans - D07-12-25-0095
- 2026-03-27 - East Storm Profile - D07-12-25-0095
- 2026-03-27 - Civil Plans - D07-12-25-0095
Status Updated
- Status: Active (Circulation Package Prepared)
Added description and 8 documents
- Status: Active (On Circulation; Initial Submission Review)
- OC Transpo proposes constructing a new enclosed parking garage to replace the existing outdoor parking lot that currently serves OC Transpo…
- 2025-08-18 - Application Summary - D07-12-25-0095
- 2025-07-16 - Geotechnical Investigation - Electrical - D07-12-25-0095
- 2025-07-10 - Site Servicing Report - D07-12-25-0095
- 2025-07-10 - Plan of Survey - D07-12-25-0095
- 2025-07-10 - Phase Two Environmental Site Assessment - D07-12-25-0095
- 2025-07-10 - Phase One Environmental Site Assessment - D07-12-25-0095
- 2025-07-10 - Drawings - Design and Construction - D07-12-25-0095
- 2024-07-16 - Geotechnical Investigation - Hydro - D07-12-25-0095
Additional Information#
| Date Initiated | 2025-07-10 |
| Ward | Ward 18 - Marty Carr |
Documents#
Related Projects#
| Project | Last Updated | Date Initiated |
|---|---|---|
1500 St-Laurent Blvd.
D07-12-22-0078 | 2022-06-03 | 2022-05-12 |