Ottawa Development Projects

Thumbnail

675 Borbridge Ave.

Last updated: 2026-07-14 · ID: D07-12-25-0045

Summary#

The proposal includes a 2-storey Catholic high school, constructed with a combination of masonry and lightweight cladding, designed to accommodate 826 students with future growth capacity to 1186. The site also incorporates a daycare facility and features include a bus lay-by drop-off zone, parking, a soccer field with running track, a basketball court, and a fenced yard.

Source: City-provided description
Status
Post Approval (Agreement Signed)
Project Type
Site Plan Control
Property Type
Education
Daycare

Building Scale (Max.) Based on elevation drawings. Values may be approximate. See sources for exact figures.
Low-rise · 2 storeys · 10.41 m

Renders#

Location#

Select a marker to view the address.

Project Updates#

2026-07-14 Status
Status Updated
  • Status: Post Approval (Agreement Signed)
2026-04-14 Status
Status Updated
  • Status: Post Approval (Receipt of Agreement from Owner Pending)
2025-11-14 Status
Status Updated
  • Status: Post Approval (Request for Agreement Received)
2025-09-27 Status
Status Updated
  • Status: Inactive (Application Approved)
2025-09-09 Status
Status Updated
  • Status: Active (Initial Review Comments Sent)
2025-07-30 Status
Status Updated
  • Status: Active (On Circulation; Initial Submission Review)
2025-07-23 Documents
Added 1 document
  • Status: Active (Circulation Package Prepared)
2025-07-17 Initial Update
Added description, 9 images and 27 documents
  • Status: Active (Community Heads Up - supporting documents to be posted later during circulation period)
  • The proposal includes a 2-storey Catholic high school, constructed with a combination of masonry and lightweight cladding, designed to acco…
  • 5 renders
  • 2 site plans
  • 1 elevation
  • 1 floor plan

Site Plans, Elevations and Floor Plans#

Additional Information#

Date Initiated2025-04-08
WardWard 22 - Steve Desroches

Documents#

TypeDocument
Application Summary2025-07-22 - Application Summary - D07-12-25-0045
Architectural Plans2025-06-20 - Architectural Drawings - D07-12-25-0045
Architectural Plans2025-04-08 - Architecture Plans - D07-12-25-0045
Architectural Plans2025-09-29 - APPROVED Site Plan Approval Report - D07-12-25-0045
Architectural Plans2025-09-29 - APPROVED Revised Overall Plan - D07-12-25-0045
Civil Engineering Report2025-06-20 - Civil Plans - D07-12-25-0045
Civil Engineering Report2025-04-08 - Civil Drawings - D07-12-25-0045
Civil Engineering Report2025-09-29 - APPROVED Civil Plans - D07-12-25-0045
Design Brief2025-06-20 - Urban Design Brief - D07-12-25-0045
Electrical Plan2025-04-08 - Site Lighting Design Compliance Letter-D07-12-25-0045
Environmental2025-07-08 - Geotechnical Investigation & Phase II ESA - D07-12-25-0045
Environmental2025-06-20 - Environmental Impact Study - D07-12-25-0045
Environmental2025-06-20 - Environment Site Assessment - Addeundum - D07-12-25-0045
Environmental2025-06-20 - Environment Site Assessment - D07-12-25-0045
Environmental2025-04-08 - Phase One Environmental Site Assessment - D07-12-25-0045
Environmental2025-04-08 - Phase II Environmental Site Assessment - D07-12-25-0045
Environmental2025-04-08 - Environmental Impact Study-D07-12-25-0045
Environmental2025-09-29 - APPROVED Phase One Environmental Site Assessment - D07-12-25-0045
Environmental2025-09-29 - APPROVED Environmental Impact Study - D07-12-25-0045
Environmental2025-09-29 - APPROVED Environment Site Assessment Addeundum - D07-12-25-0045
Landscape Plan2025-06-20 - Landscape Plan - D07-12-25-0045
Landscape Plan2025-04-08 - Landscape Plan - D07-12-25-0045
Landscape Plan2025-09-29 - APPROVED Landscape Plan - D07-12-25-0045
Noise Study2025-04-08 - Noise Control Study - D07-12-25-0045
Noise Study2025-09-29 - APPROVED Noise Control Study - D07-12-25-0045
Planning2025-04-08 - Planning Rationale - D07-12-25-0045
Site Servicing2025-06-20 - Site Servicing Study - D07-12-25-0045
Site Servicing2025-04-08 - Site Servicing Study-D07-12-25-0045
Site Servicing2025-09-29 - APPROVED Servicing & Stormwater Management Report - D07-12-25-0045
Surveying2025-04-08 - Survey- D07-12-25-0045
Transportation Analysis2025-06-20 - Transportation Impact Assessment - D07-12-25-0045
Transportation Analysis2025-04-08 - Transportation Impact Assessment-D07-12-25-0045
Transportation Analysis2025-09-29 - APPROVED Transportation Impact Assessment - D07-12-25-0045
Tree Information and Conservation2025-06-25 - Tree Conservation Report - Phase 2 - D07-12-25-0045
Tree Information and Conservation2025-04-08 - Tree Conservation Report - Phase 1-D07-12-25-0045
Tree Information and Conservation2025-09-29 - APPROVED Tree Conservation Report Phase 2 - D07-12-25-0045
Tree Information and Conservation2025-09-29 - APPROVED Tree Conservation Report Phase 1 - D07-12-25-0045
2025-06-20 - Roadway Modifications - D07-12-25-0045
2025-06-20 - Cover Page for Drawings - D07-12-25-0045
2025-04-08 - Cover Page - D07-12-25-0045