Summary#
Gastops Ltd proposes constructing one two-storey, freestanding building totaling 4,605 square metres for light industrial use and office space within the Riverside South Employment Lands.
Source:
City-provided description
and 2024-12-13 - Urban Design Brief - D07-12-24-0170 (Page 1)
Status
Inactive (Agreement Registered - Final Legal Clearance Given)
Inactive (Agreement Registered - Final Legal Clearance Given)
Project Type
Site Plan Control
Site Plan Control
Property Type
Commercial
Industrial
Commercial
Industrial
Building Scale (Max.)
Based on elevation drawings. Values may be approximate. See sources for exact figures.
Low-rise · 2 storeys
· 8.9 m
Data Quality Note
Height was partially estimated using visual scale. This may be approximate.
Massing Diagrams#
Location#
Select a marker to view the address.
Project Updates#
Status Updated
- Status: Inactive (Agreement Registered - Final Legal Clearance Given)
Status Updated
- Status: Post Approval (Agreement Signed)
Status Updated
- Status: Post Approval (Agreement Package Received from Owner)
Status Updated
- Status: Post Approval (Receipt of Agreement from Owner Pending)
Status Updated
- Status: Post Approval (Request for Agreement Received)
Status Updated
- Status: Inactive (Notice of Decision Sent)
Added 1 image and 6 documents
- 2025-06-11 - Site Plan - D07-12-24-0170
- 2025-06-11 - Site Grading Plan & Site Servicing Plan - D07-12-24-0170
- 2025-06-11 - Servicing & Stormwater Management Report Revision 4 - D07-12-24-0170
- 2025-06-11 - Landscape Plan Details and Canopy Projections - D07-12-24-0170
- 2025-06-11 - Elevations & Perspectives - D07-12-24-0170
- 2025-06-11 - Draft SPAR - D07-12-24-0170
Status Updated
- Status: Active (Applicant Concurs)
Status Updated
- Status: Active (Draft Report Sent for Response)
Status Updated
- Status: Active (Additional Submission Deemed Adequate)
Added 6 images and 10 documents
- 6 site plans
- 2025-04-16 - Revised Servicing & Stormwater Management Report - D07-12-24-0170
- 2025-04-16 - Revised L1 3 Gastops HQ Tree Canopy Projection Revision No 4 - D07-12-24-0170
- 2025-04-16 - Revised L1 2 Gastops HQ Landsacpe Details Revision No 4 - D07-12-24-0170
- 2025-04-16 - Revised L1 1 Gastops HQ Landscape Plan Revision No 4 - D07-12-24-0170
- 2025-04-16 - Revised C102 Site Servicing Plan Revision No 4 - D07-12-24-0170
- 2025-04-16 - Revised C101 Site Grading Plan Revision No 4 - D07-12-24-0170
- 2025-04-16 - Revised A300 Elevations Revision No 11 - D07-12-24-0170
- 2025-04-16 - Revised A100 Site Plan Revision No 11 - D07-12-24-0170
- 2025-04-16 - Grading and Site Servicing Plan Review Memorandum - D07-12-24-0170
- 2025-04-16 - Design Brief Phase 1 - D07-12-24-0170
Status Updated
- Status: File Pending (Application File Pending)
Status Updated
- Status: Active (On Circulation; Initial Submission Review)
Added description, height, 6 images and 17 documents
- Status: Active (Circulation Package Prepared)
- Gastops Ltd proposes constructing one two-storey, freestanding building totaling 4,605 square metres for light industrial use and office sp…
- Height: 2 storeys, 8.9 m
- 1 massing diagram
- 1 site plan
- 4 elevations
- 2025-03-03 - Application Summary - D07-12-24-0170
- 2025-02-24 - Site Plan - D07-12-24-0170
- 2025-02-10 - Tree Canopy Projections - D07-12-24-0170
- 2025-02-10 - Site Servicing Plan - D07-12-24-0170
- 2025-02-10 - Site Grading Plan - D07-12-24-0170
- 2025-02-10 - Servicing & Stormwater Management Report - D07-12-24-0170
- 2025-02-10 - Landscape Plan - D07-12-24-0170
- 2025-02-10 - Landscape Details - D07-12-24-0170
- 2024-12-23 - Topographic Survey - D07-12-24-0170
- 2024-12-13 - Urban Design Brief - D07-12-24-0170
- 2024-12-13 - Transportation Impact Assessment - D07-12-24-0170
- 2024-12-13 - Preliminary Construction Management Plan - D07-12-24-0170
- 2024-12-13 - Plan 4M-1746 - D07-12-24-0170
- 2024-12-13 - Phase 1 Environmental Site Assessment - D07-12-24-0170
- 2024-12-13 - Geotechnical Report - D07-12-24-0170
- 2024-12-13 - Environmental Noise Control Study - D07-12-24-0170
- 2024-12-13 - Elevations - D07-12-24-0170
Site Plans, Elevations and Floor Plans#
Additional Information#
| Date Initiated | 2024-12-13 |
| Ward | Ward 22 - Steve Desroches |
Documents#
Related Projects#
| Project | Last Updated | Date Initiated |
|---|---|---|
4020 Spratt Rd.3700 Twin Falls Pl.
D07-16-22-0014 | 2024-09-25 | 2022-07-14 |
4020 Spratt Rd.3700 Twin Falls Pl.
D02-02-22-0070 | 2023-12-07 | 2022-07-14 |