The proposal encompasses three buildings: a seven-storey structure housing 565 residential units and the relocated Parkway House on the ground floor, a sixteen-storey building, and a twenty-eight-storey building.

Source: City-provided description
Status
Post Approval (Request for Agreement Received)
Project Type
Site Plan Control
Property Type
Residential

Building Scale (Max.) Derived from project description and planning application details. Values may be approximate.
High-rise · 28 storeys

Renders#

Location#

Select a marker to view the address.

Project Updates#

2025-08-29 Status
Status Updated
  • Status: Post Approval (Request for Agreement Received)
2025-08-13 Documents
Added 24 documents
2025-05-08 Status
Status Updated
  • Status: Inactive (Notice of Decision Sent)
2025-04-26 Status
Status Updated
  • Status: Active (Draft Report Sent for Response)
2025-03-26 Documents
Added 1 document
  • Status: Active (On Circulation; Initial Submission Review)
2025-03-21 Initial Update
Added description and 52 documents
  • Status: Active (Circulation Package Prepared)
  • The proposed development consists of three buildings; one 7-storey building incorporating Parkway House facility on the ground floor with r…

Site Plans, Elevations and Floor Plans#

Additional Information#

Date Initiated2024-12-04
WardWard 7 - Theresa Kavanagh

Documents#

TypeDocument
Application Summary2025-03-25 - Application Summary - D07-12-24-0161
Application Summary2025-03-21 - Application Summary - D07-12-24-0161
Application Summary2025-03-21 - Application Summary - D07-12-24-0161
Architectural Plans2025-02-24 - Stormtech Chambers Notes and Details Sheet - D07-12-24-0161
Architectural Plans2025-02-24 - Sanitary Drainage Plan - D07-12-24-0161
Architectural Plans2025-02-24 - Regina Street Plan and Profile - D07-12-24-0161
Architectural Plans2025-02-24 - Architectural Drawings - D07-12-24-0161
Architectural Plans2024-12-03 - Stormtech Chambers Notes and Details Sheet - D07-12-24-0161
Architectural Plans2024-12-03 - Sanitary Drainage Plan - D07-12-24-0161
Architectural Plans2024-12-03 - Plan and Profile STA 0+000 to STA 0+060 - D07-12-24-0161
Architectural Plans2024-12-03 - Architectural Plans - D07-12-24-0161
Architectural Plans2025-05-02 - APPROVED Stormtech Chambers Notes and Details Sheet - D07-12-24-0161
Architectural Plans2025-05-02 - APPROVED Sanitary Drainage Plan - D07-12-24-0161
Architectural Plans2025-05-02 - APPROVED Regina Street Plan and Profile - D07-12-24-0161
Architectural Plans2025-05-02 - APPROVED Elevations - D07-12-24-0161
Architectural Plans2025-06-18 - Street Plan - D07-12-24-0161
Architectural Plans2025-06-18 - Site Plan Resubmission - D07-12-24-0161
Architectural Plans2025-06-18 - Sanitary Drainage Plan - D07-12-24-0161
Architectural Plans2025-08-11 - APPROVED Stormtech Chambers Notes and Details Sheet - D07-12-24-0161
Architectural Plans2025-08-11 - APPROVED Site Plan Approval Report - D07-12-24-0161
Architectural Plans2025-08-11 - APPROVED Site Plan - D07-12-24-0161
Architectural Plans2025-08-11 - APPROVED Sanitary Drainage Plan - D07-12-24-0161
Architectural Plans2025-08-11 - APPROVED Regina Street Plan and Profile - D07-12-24-0161
Architectural Plans2025-08-11 - APPROVED Elevations - D07-12-24-0161
Design Brief2024-12-03 - Design Brief - D07-12-24-0161
Design Brief2025-05-02 - APPROVED Design Brief - D07-12-24-0161
Environmental2025-02-24 - Phase I-ESA Update - D07-12-24-0161
Environmental2025-02-24 - Phase I ESA - D07-12-24-0161
Environmental2024-12-03 - Phase I ESA Update - D07-12-24-0161
Environmental2025-05-02 - APPROVED Phase I-ESA Update - D07-12-24-0161
Environmental2025-05-02 - APPROVED Phase I ESA - D07-12-24-0161
Environmental2025-08-11 - APPROVED Phase I-ESA Update - D07-12-24-0161
Environmental2025-08-11 - APPROVED Phase I ESA - D07-12-24-0161
Erosion And Sediment Control Plan2025-02-24 - Erosion Control and Details Sheet - D07-12-24-0161
Erosion And Sediment Control Plan2024-12-03 - Erosion Control and Details Sheet - D07-12-24-0161
Erosion And Sediment Control Plan2025-05-02 - APPROVED Erosion Control and Details Sheet - D07-12-24-0161
Erosion And Sediment Control Plan2025-06-18 - Erosion Control - D07-12-24-0161
Erosion And Sediment Control Plan2025-08-11 - APPROVED Erosion Control and Details Sheet - D07-12-24-0161
Existing Conditions2025-02-24 - Existing Conditions and Removals Plan - D07-12-24-0161
Existing Conditions2024-12-03 - Existing Conditions and Removals Plan - D07-12-24-0161
Existing Conditions2025-05-02 - APPROVED Existing Conditions and Removals Plan - D07-12-24-0161
Existing Conditions2025-06-18 - Existing Conditions and removal - D07-12-24-0161
Geotechnical Report2025-02-24 - Grading Plan Ultimate (Phase 1 & 2) - D07-12-24-0161
Geotechnical Report2025-02-24 - Grading Plan Interim (Phase 1) - D07-12-24-0161
Geotechnical Report2025-02-24 - Geotechnical Investigation - D07-12-24-0161
Geotechnical Report2024-12-03 - Grading Plan - D07-12-24-0161
Geotechnical Report2024-12-03 - Geotechnical Investigation - D07-12-24-0161
Geotechnical Report2025-06-18 - Grading Plan Phase 1&2 - D07-12-24-0161
Geotechnical Report2025-06-18 - Grading Plan - D07-12-24-0161
Geotechnical Report2025-06-18 - Geotechnical Investigation Updated - D07-12-24-0161
Geotechnical Report2025-08-11 - APPROVED Grading Plan Ultimate - D07-12-24-0161
Geotechnical Report2025-08-11 - APPROVED Grading Plan Interim - D07-12-24-0161
Geotechnical Report2025-08-11 - APPROVED Geotechnical Investigation Updated - D07-12-24-0161
Landscape Plan2025-02-24 - Landscape Plans - D07-12-24-0161
Landscape Plan2024-12-03 - Landscape Plans - D07-12-24-0161
Landscape Plan2025-06-18 - Landscape Plan - D07-12-24-0161
Landscape Plan2025-08-11 - APPROVED Landscape Plans - D07-12-24-0161
Noise Study2024-12-03 - Transportation Noise and Vibration Assessment - D07-12-24-0161
Noise Study2025-05-02 - APPROVED Transportation Noise and Vibration Assessment - D07-12-24-0161
Noise Study2025-08-11 - APPROVED Transportation Noise and Vibration Assessment - D07-12-24-0161
Planning2025-02-24 - Zoning Diagram - D07-12-24-0161
Planning2025-02-24 - Zoning Confirmation Report - D07-12-24-0161
Planning2024-12-03 - Zoning Confirmation Report - D07-12-24-0161
Site Servicing2025-02-24 - Site Servicing Plan Ultimate (Phase 1 & 2) - D07-12-24-0161
Site Servicing2025-02-24 - Site Servicing Plan Interim (Phase 1) - D07-12-24-0161
Site Servicing2025-02-24 - Site Servicing and SWM Report - D07-12-24-0161
Site Servicing2024-12-03 - Site Servicing Plan Ultimate (Phase 1 & 2) - D07-12-24-0161
Site Servicing2024-12-03 - Site Servicing Plan Interim (Phase 1) - D07-12-24-0161
Site Servicing2024-12-03 - Site Servicing & SWM Report - D07-12-24-0161
Site Servicing2025-06-18 - Site servicing Plan Phase 1 and 2 - D07-12-24-0161
Site Servicing2025-06-18 - Site servicing Plan - D07-12-24-0161
Site Servicing2025-06-18 - Site servicing and stormwater Management Report - D07-12-24-0161
Site Servicing2025-08-11 - APPROVED Site Servicing Plan Ultimate - D07-12-24-0161
Site Servicing2025-08-11 - APPROVED Site Servicing Plan Interim - D07-12-24-0161
Site Servicing2025-08-11 - APPROVED Site servicing and stormwater Management Report - D07-12-24-0161
Stormwater Management2025-02-24 - Storm Drainage Plan - D07-12-24-0161
Stormwater Management2025-02-24 - Existing Storm Drainage Plan - D07-12-24-0161
Stormwater Management2024-12-03 - Storm Drainage Plan - D07-12-24-0161
Stormwater Management2024-12-03 - Existing Storm Drainage Plan - D07-12-24-0161
Stormwater Management2025-05-02 - APPROVED Storm Drainage Plan - D07-12-24-0161
Stormwater Management2025-05-02 - APPROVED Existing Storm Drainage Plan - D07-12-24-0161
Stormwater Management2025-06-18 - Storm Drainage Plan - D07-12-24-0161
Stormwater Management2025-08-11 - APPROVED Storm Drainage Plan - D07-12-24-0161
Surveying2025-02-24 - TOPO Plan of Survey - D07-12-24-0161
Surveying2024-12-03 - TOPO Sketch - D07-12-24-0161
Transportation Analysis2024-12-03 - Transportation Impact Assessment - D07-12-24-0161
Transportation Analysis2025-08-11 - APPROVED Transportation Impact Assessment - D07-12-24-0161
Tree Information and Conservation2025-02-24 - Tree Conservation Report - D07-12-24-0161
Tree Information and Conservation2024-12-03 - Tree Conservation Report - D07-12-24-0161
Tree Information and Conservation2025-06-18 - Tree Conservation Report - D07-12-24-0161
Tree Information and Conservation2025-08-11 - APPROVED Tree Conservation Report - D07-12-24-0161
Wind Study2024-12-03 - Pedestrian Level Wind Study Addendum - D07-12-24-0161
Wind Study2024-12-03 - Pedestrian Level Wind Study - D07-12-24-0161
Wind Study2025-05-02 - APPROVED Pedestrian Level Wind Study - D07-12-24-0161
Wind Study2025-08-11 - APPROVED Pedestrian Level Wind Study Addendum - D07-12-24-0161
Wind Study2025-08-11 - APPROVED Pedestrian Level Wind Study - D07-12-24-0161
2025-02-24 - Redi Rock Retaining Wall Design (RR5) - D07-12-24-0161
2025-02-24 - Redi Rock Retaining Wall Design (RR3 & RR4) - D07-12-24-0161
2025-02-24 - Redi Rock Retaining Wall Design (RR1 & RR2) - D07-12-24-0161
2025-02-24 - Notes and Legends Drawing - D07-12-24-0161
2024-12-03 - Notes and Legends Drawing - D07-12-24-0161
2024-12-03 - Letter of Reliance - D07-12-24-0161
2025-05-02 - APPROVED Redi Rock Retaining Wall Design - RR1 and RR2 - D07-12-24-0161
2025-05-02 - APPROVED Notes and Legends Drawing - D07-12-24-0161
2025-05-02 - APPROVED Delegated Authority Report - D07-12-24-0161
2025-06-18 - Transport Imapact Assesment - D07-12-24-0161
2025-06-18 - site pavement Marking - D07-12-24-0161
2025-06-18 - Redi Rock Retaining Wall Design (RR5) - D07-12-24-0161
2025-06-18 - Redi Rock Retaining Wall Design (RR3 & RR4) - D07-12-24-0161
2025-06-18 - Redi Rock Retaining Wall Design - D07-12-24-0161
2025-06-18 - Notes and Legends - D07-12-24-0161
2025-08-11 - APPROVED Retaining Wall Designs - D07-12-24-0161
2025-08-11 - APPROVED Notes and Legends Drawing - D07-12-24-0161