363 Entrepreneur Cres.#
Last updated: 2026-01-28 · ID: D07-12-24-0100
Summary#
The development proposed consists of an industrial warehouse. The warehouse will serve predominantly as storage but will also be used in the construction and maintenance of props equipment. An entrance branching off Entrepreneur Crescent will provide vehicular access to the site. A gravel driveway has been proposed along the east face of the building, providing access to the rear paved loading and vehicle maneuverability area. Parking will be provided within the gravel area in front of the south face of the building. The balance of the site will be grassed area and landscaping elements.
Status
Inactive (Agreement Registered - Securities Held)
Location#
Select a marker to view the address.
Project Updates#
Status Updated
- Status: Inactive (Agreement Registered - Securities Held)
Status Updated
- Status: Post Approval (Agreement Signed)
Status Updated
- Status: Post Approval (Receipt of Agreement from Owner Pending)
Status Updated
- Status: Inactive (Signed Letter of Undertaking Received)
Status Updated
- Status: Post Approval (Signed Letter of Undertaking Received)
Added 2 images and 20 documents
- 1 site plan
- 1 floor plan
- 2025-04-22 -Zoning Confirmation Report Rev2 - D07-12-24-0100
- 2025-04-22 - Urban Design Brief - D07-12-24-0100
- 2025-04-22 - TANK SPECS - D07-12-24-0100
- 2025-04-22 - Storm Water Management Report - D07-12-24-0100
- 2025-04-22 - SEPTIC SECTION - D07-12-24-0100
- 2025-04-22 - SEPTIC LAYOUT - D07-12-24-0100
- 2025-04-22 - Report Hydrogeological Assessment - D07-12-24-0100
- 2025-04-22 - PUMP SPECS - D07-12-24-0100
- 2025-04-22 - PUMP CHAMBER - D07-12-24-0100
- 2025-04-22 - Proposed Ground Floor Layout - D07-12-24-0100
- 2025-04-22 - PLAN OF SURVEY - D07-12-24-0100
- 2025-04-22 - Landscape Plan - D07-12-24-0100
- 2025-04-22 - Geotechnical Investigation Proposed Warehouse - D07-12-24-0100
- 2025-04-22 - FLOW CALCULATIONS - D07-12-24-0100
- 2025-04-22 - Environmental Site Assessment Phase 2 - D07-12-24-0100
- 2025-04-22 - Environmental Site Assessment Phase 1 - D07-12-24-0100
- 2025-04-22 - Environmental Impact Statement - D07-12-24-0100
- 2025-04-22 - DWILSON BLDG2 OLYMPIA - D07-12-24-0100
- 2025-04-22 - Design Brief - D07-12-24-0100
- 2025-04-22 - Civil Plans - D07-12-24-0100
Status Updated
- Status: Inactive (Notice of Decision Sent)
Added 1 document
- Status: Inactive (Application Approved)
Status Updated
- Status: Active (Applicant Concurs)
Status Updated
- Status: Active (Comment Period has Ended/Issue Resolution)
Status Updated
- Status: File Pending (Application File Pending)
Status Updated
- Status: Active (Initial Review Comments Sent)
Added description
- Status: Active (Circulation Package Prepared)
- The development proposed consists of an industrial warehouse. The warehouse will serve predominantly as storage but will also be used in th…
Site Plans, Elevations and Floor Plans#
Additional Information#
| Date Initiated | 2024-08-29 |
| Ward | Ward 20 - Isabelle Skalski |