Ottawa Development Projects

2545 9th Line Rd.#

Last updated: 2025-08-02 ยท ID: D07-12-23-0011

Summary#

The City of Ottawa has received an Official Plan Amendment, Zoning By-law Amendment and Site Plan Control application to convert the existing buildings from a mushroom growing operation to soil packaging with potential for future leaf and yard waste composting.

Status
Inactive (Notice of Decision Sent)

Location#

Select a marker to view the address.

Additional Information#

Date Initiated2023-02-03
WardWard 20 - Isabelle Skalski

Documents#

TypeDocument
Adequacy Of Public Services2024-02-26 - Assessment of Adequacy of Servicing Report - D07-12-23-0011
Adequacy Of Public Services2023-06-30 - Assessment of Adequacy of Servicing Report - D07-12-23-0011
Adequacy Of Public Services2023-02-03 - Assessment of Adequacy of Servicing Report - D07-12-23-0011
Adequacy Of Public Services2024-08-12 - Assessment of Adequacy of Servicing Report - D07-12-23-0011
Adequacy Of Public Services2024-10-21 - Assessment of Adequacy of Servicing Report - D07-12-23-0011
Adequacy Of Public Services2025-07-31 - APPROVED Assessment of Adequacy of Servicing Report - D07-12-23-0011
Application Summary2023-08-10 - Application Summary - D07-12-23-0011
Architectural Plans2024-02-26 - Site and Landscape Plan - D07-12-23-0011
Architectural Plans2023-06-30 - Site and Landscape Plan -D07-12-23-0011
Architectural Plans2023-06-30 - Septic Designs - Plan - D07-12-23-0011
Architectural Plans2023-02-03 - Site and Landscape Plan -D07-12-23-0011
Architectural Plans2024-08-12 - Site and Landscape Plan - Additional Info Sheet - D07-12-23-0011
Architectural Plans2024-10-21 - ASB Greenworld Site and Landscape Plan - D07-12-23-0011
Architectural Plans2024-10-21 - ASB Greenworld Site and Landscape Plan - Additional Info Sheet - D07-12-23-0011
Architectural Plans2025-07-31 - APPROVED Septic System Design Plan - D07-12-23-0011
Architectural Plans2025-07-31 - APPROVED ASB Greenworld Site and Landscape Plan Additional Info - D07-12-23-0011
Architectural Plans2025-07-31 - APPROVED ASB Greenworld Site and Landscape Plan - D07-12-23-0011
Geotechnical Report2024-02-26 - Hydrogeological Assessment - D07-12-23-0011
Geotechnical Report2023-06-30 - Hydrogeological Assessment - D07-12-23-0011
Geotechnical Report2023-02-03 - Hydrogeological Assessment - D07-12-23-0011
Geotechnical Report2024-08-12 - Hydrogeological Assessment - D07-12-23-0011
Geotechnical Report2024-10-21 - Hydrogeological Assessment - D07-12-23-0011
Geotechnical Report2025-07-31 - APPROVED Hydrogeological Assessment - D07-12-23-0011
Planning2023-06-30 - Planning Report - D07-12-23-0011
Planning2023-02-03 - Planning Report - D07-12-23-0011
Surveying2023-02-03 - Topographic Plan - D07-12-23-0011
Surveying2023-02-03 - Letter - Topographic Survey - D07-12-23-0011
Transportation Analysis2023-02-03 - Transportation Impact Assessment Letter - D07-12-23-0011
Transportation Analysis2025-07-31 - APPROVED Traffic Plan - D07-12-23-0011
Tree Information and Conservation2023-02-03 - Tree Conservation Report - D07-12-23-0011
Tree Information and Conservation2025-07-31 - APPROVED Tree Conservation Report - D07-12-23-0011
2024-02-26 - Septic Design - D07-12-23-0011
2023-06-30 - Design Calculations - D07-12-23-0011
2023-02-03 - Scoped Environmental Impact Statement & Natural Heritage Study - D07-12-23-0011
2025-07-31 - APPROVED Scoped Environmental Impact Statement & Natural Heritage Study - D07-12-23-
2025-07-31 - APPROVED Delegated Authority Report - D07-12-23-0011