Ottawa Development Projects

2625 Sheffield Rd.#

Last updated: 2025-02-19 · ID: D07-12-22-0149

Summary#

The proposal is for one industrial warehouse distribution facility, which will be a low-rise structure with a maximum height of 13.64m and a maximum building coverage of 35%. This development proposes a Gross Floor Area of 24,484m2 and includes 884 parking spaces, of which 7 are accessible, alongside 17 bicycle parking spaces.

Status
Post Approval (Agreement Signed)
Property Type
Industrial

Building Scale (Max.) Based on elevation drawings. Values may be approximate. See sources for exact figures.
Low-rise · 3 storeys Data Quality Note Text was extracted using optical character recognition. This may introduce artifacts or misreads.

Location#

Select a marker to view the address.

Project Updates#

2025-02-19 Status
Status Updated
  • Status: Post Approval (Agreement Signed)
2023-06-26 Initial Update
Added description, 2 images and 25 documents

Site Plans, Elevations and Floor Plans#

Additional Information#

Date Initiated2022-10-18
WardWard 18 - Marty Carr

Documents#

TypeDocument
Application Summary2022-11-16 - Application Summary - D07-12-22-0149
Architectural Plans2023-06-21 - Approved Architectural Plans - D07-12-22-0149
Architectural Plans2022-10-17 - Site Plan - D07-12-22-0149
Civil Engineering Report2023-06-21 - Approved Civil Plans - D07-12-22-0149
Design Brief2022-11-16 - Planning Rationale and Design Brief - D07-12-22-0149
Design Brief2022-10-17 - Planning Rationale and Design Brief- - D07-12-22-0149
Electrical Plan2022-10-17 - Site Lighting Certificate - D07-12-22-0149
Electrical Plan2022-10-17 - Electrical Legend - D07-12-22-0149
Environmental2022-10-17 - Phase Two Environmental Site Assessment -D07-12-22-0149
Environmental2022-10-17 - Phase One Environmental Site Assessment - D07-12-22-0149
Existing Conditions2022-10-17 - Existing Conditions & Removals D07-12-22-0149
Geotechnical Report2023-06-21 - Geotechnical Technical Memorandum Rev3 - D07-12-22-0149
Geotechnical Report2022-10-17 - Memo - Geotechnical Invesitgation - D07-12-22-0149
Landscape Plan2023-06-21 - Approved Landscape Plans - D07-12-22-0149
Notification2023-07-14 - Commence Work Notification - D07-12-22-0149
Site Servicing2023-06-21 - Approved Site Servicing Report - D07-12-22-0149
Site Servicing2022-10-17 - Site Servicing Report- D07-12-22-0149
Surveying2022-10-17 - Plan of Survey - D07-12-22-0149
Transportation Analysis2023-06-21 - Traffic Impact Assessment Memorandum - D07-12-22-0149
Transportation Analysis2022-11-16 - Traffic Impact Assessment Update Step 2 and 3 - D07-12-22-0149
Transportation Analysis2022-11-16 - Traffic Impact Assessment Step 4 Update - D07-12-22-0149
Tree Information and Conservation2023-06-21 - Approved Tree Conservation Report - D07-12-22-0149
Tree Information and Conservation2022-10-17 - Tree Management Plan - D07-12-22-0149
Tree Information and Conservation2022-10-17 - Tree Conservation Report - D07-12-22-0149
2023-06-21 - Signed Delegated Authority Report - D07-12-22-0149