Summary#

Construction of four, nine-storey mid-rise apartment buildings, each with 106 units, for a total of 424 units and an amenity building for the use of the residents. The remainder of the site is to be developed with a balance of amenity areas, as well as surface parking and drive aisles. One level of underground parking is proposed under each of the apartment and amenity building.

Status
File Pending (Application File Pending)

Building Scale (Max.) Based on elevation drawings. Values may be approximate. See sources for exact figures.
Mid-rise · 9 storeys · 31 m

Renders#

Location#

Select a marker to view the address.

Site Plans, Elevations and Floor Plans#

  • Image from page 28 of the file '2021-05-18 - Urban Design Brief - D07-12-21-0062'
  • Image from page 25 of the file '2021-05-18 - Urban Design Brief - D07-12-21-0062'
  • Image from page 26 of the file '2021-05-18 - Urban Design Brief - D07-12-21-0062'
  • Image from page 27 of the file '2021-05-18 - Urban Design Brief - D07-12-21-0062'
  • Image from page 11 of the file '2021-05-18 - Urban Design Brief - D07-12-21-0062'
  • Image from page 27 of the file '2021-05-18 - Urban Design Brief - D07-12-21-0062'
  • Image from page 29 of the file '2021-05-18 - Urban Design Brief - D07-12-21-0062'
  • Image from page 33 of the file '2021-05-18 - Urban Design Brief - D07-12-21-0062'
  • Construction site plan for project from page 32 of the file '2021-05-18 - Urban Design Brief - D07-12-21-0062'
  • Construction site plan for project from page 17 of the file '2021-05-18 - Urban Design Brief - D07-12-21-0062'
  • Construction site plan for project from page 36 of the file '2021-05-18 - Urban Design Brief - D07-12-21-0062'
  • Construction site plan for project from page 19 of the file '2021-05-18 - Urban Design Brief - D07-12-21-0062'
  • Construction site plan for project from page 3 of the file '2021-05-18 - Urban Design Brief - D07-12-21-0062'
  • Construction site plan for project from page 20 of the file '2021-05-18 - Urban Design Brief - D07-12-21-0062'
  • Construction site plan for project from page 4 of the file '2021-05-18 - Urban Design Brief - D07-12-21-0062'
  • Construction site plan for project from page 10 of the file '2021-05-18 - Urban Design Brief - D07-12-21-0062'
  • Construction site plan for project from page 6 of the file '2021-05-18 - Urban Design Brief - D07-12-21-0062'
  • Construction site plan for project from page 34 of the file '2021-05-18 - Urban Design Brief - D07-12-21-0062'
  • Floor plan for project from page 18 of the file '2021-05-18 - Urban Design Brief - D07-12-21-0062'
  • Floor plan for project from page 20 of the file '2021-05-18 - Urban Design Brief - D07-12-21-0062'
  • Floor plan for project from page 21 of the file '2021-05-18 - Urban Design Brief - D07-12-21-0062'
  • Floor plan for project from page 24 of the file '2021-05-18 - Urban Design Brief - D07-12-21-0062'
  • Floor plan for project from page 22 of the file '2021-05-18 - Urban Design Brief - D07-12-21-0062'
  • Image from page 28 of the file '2021-05-18 - Urban Design Brief - D07-12-21-0062'
  • Image from page 25 of the file '2021-05-18 - Urban Design Brief - D07-12-21-0062'
  • Image from page 26 of the file '2021-05-18 - Urban Design Brief - D07-12-21-0062'
  • Image from page 27 of the file '2021-05-18 - Urban Design Brief - D07-12-21-0062'
  • Image from page 11 of the file '2021-05-18 - Urban Design Brief - D07-12-21-0062'
  • Image from page 27 of the file '2021-05-18 - Urban Design Brief - D07-12-21-0062'
  • Image from page 29 of the file '2021-05-18 - Urban Design Brief - D07-12-21-0062'
  • Image from page 33 of the file '2021-05-18 - Urban Design Brief - D07-12-21-0062'
  • Construction site plan for project from page 32 of the file '2021-05-18 - Urban Design Brief - D07-12-21-0062'
  • Construction site plan for project from page 17 of the file '2021-05-18 - Urban Design Brief - D07-12-21-0062'
  • Construction site plan for project from page 36 of the file '2021-05-18 - Urban Design Brief - D07-12-21-0062'
  • Construction site plan for project from page 19 of the file '2021-05-18 - Urban Design Brief - D07-12-21-0062'
  • Construction site plan for project from page 3 of the file '2021-05-18 - Urban Design Brief - D07-12-21-0062'
  • Construction site plan for project from page 20 of the file '2021-05-18 - Urban Design Brief - D07-12-21-0062'
  • Construction site plan for project from page 4 of the file '2021-05-18 - Urban Design Brief - D07-12-21-0062'
  • Construction site plan for project from page 10 of the file '2021-05-18 - Urban Design Brief - D07-12-21-0062'
  • Construction site plan for project from page 6 of the file '2021-05-18 - Urban Design Brief - D07-12-21-0062'
  • Construction site plan for project from page 34 of the file '2021-05-18 - Urban Design Brief - D07-12-21-0062'
  • Floor plan for project from page 18 of the file '2021-05-18 - Urban Design Brief - D07-12-21-0062'
  • Floor plan for project from page 20 of the file '2021-05-18 - Urban Design Brief - D07-12-21-0062'
  • Floor plan for project from page 21 of the file '2021-05-18 - Urban Design Brief - D07-12-21-0062'
  • Floor plan for project from page 24 of the file '2021-05-18 - Urban Design Brief - D07-12-21-0062'
  • Floor plan for project from page 22 of the file '2021-05-18 - Urban Design Brief - D07-12-21-0062'

Additional Information#

Date Initiated2021-05-18
WardWard 4 - Cathy Curry

Documents#

TypeDocument
Application Summary2021-05-26 - Application Summary - D07-12-21-0062
Archaelogical Assessment2021-05-18 - Archaeological Assessment - D07-12-21-0062
Architectural Plans2021-05-18 - Plan 4M-1554 - D07-12-21-0062
Architectural Plans2021-05-18 - Architectural Package - D07-12-21-0062
Civil Engineering Report2021-05-18 - Civil Plans - D07-12-21-0062
Design Brief2021-05-18 - Urban Design Brief - D07-12-21-0062
Electrical Plan2021-05-18 - Electrical Layout Site Plan - D07-12-21-0062
Environmental2021-05-18 - Phase 1 Environmental Site Assessment - D07-12-21-0062
Geotechnical Report2021-05-18 - Geotechnical Investigation - D07-12-21-0062
Landscape Plan2021-05-18 - Landscape Plan and Details - D07-12-21-0062
Noise Study2021-05-18 - Noise Feasibility Study - D07-12-21-0062
Planning2021-05-18 - Planning Rationale - D07-12-21-0062
Shadow Study2021-05-18 - Shadow Study - D07-12-21-0062
Site Servicing2021-05-18 - Servicing and Stormwater Management Report - D07-12-21-0062
Surveying2021-05-18 - Topographic Sketch - D07-12-21-0062
Tree Information and Conservation2021-05-18 - Environmental Impact Statement and Tree Conservation Report Update - D07-12-21-0062