145 Loretta Ave. N./951 Gladstone Ave.#
Last updated: 2026-05-06 · ID: D07-12-21-0053
Summary#
Site redevelopment, preserving Standard Bread Building and including: Retail, Office, Residential (3 towers at 35, 33, and 30 storeys); Underground parking (570 spaces). The proposal is to accommodate a new mixed-use development program on the site. The proposed development consists of elements containing approximately 846residential units, approximately 1,600 square metres of retail space and 16,450 square metres of office space.
Status
Post Approval (Request for Agreement Received)
Post Approval (Request for Agreement Received)
Type
Site Plan Control
Site Plan Control
Building Scale (Max.)
Based on elevation drawings. Values may be approximate. See sources for exact figures.
Low-rise · 1 storey
Data Quality Note
Text was extracted using optical character recognition. This may introduce artifacts or misreads.
Renders#
Location#
Select a marker to view the address.
Project Updates#
Status Updated
- Status: Post Approval (Request for Agreement Received)
Added description
- Updated description: Site redevelopment, preserving Standard Bread Building and including: Retail, Office, Residential (3 towers at 35, 33, and 30 storeys); Und…
Status Updated
- Status: Inactive (Notice of Decision Sent)
Added 29 documents
- 2026-02-26 - APPROVED Tree Conservation Report - D07-12-21-0053
- 2026-02-26 - APPROVED Transportation Imapct Assessment - D07-12-21-0053
- 2026-02-26 - APPROVED TIA Update Memo - D07-12-21-0053
- 2026-02-26 - APPROVED Stormwater Management Report - D07-12-21-0053
- 2026-02-26 - APPROVED Stage 2 Cultural Heritage Impact Statement - D07-12-21-0053
- 2026-02-26 - APPROVED Site Plan Phase 1 - D07-12-21-0053
- 2026-02-26 - APPROVED Site Plan Approval Report - D07-12-21-0053
- 2026-02-26 - APPROVED Servicing Report - D07-12-21-0053
- 2026-02-26 - APPROVED Servicing Profile & Details - D07-12-21-0053
- 2026-02-26 - APPROVED Scoped Environmental Impact Statement - D07-12-21-0053
- 2026-02-26 - APPROVED Remedial Action Plan - D07-12-21-0053
- 2026-02-26 - APPROVED Phase 2 Proximity Report - D07-12-21-0053
- 2026-02-26 - APPROVED Phase 2 Environmental Site Assessment - D07-12-21-0053
- 2026-02-26 - APPROVED Phase 2 Conceptual Site Model - D07-12-21-0053
- 2026-02-26 - APPROVED Phase 1 Environmental Site Assessment Update - D07-12-21-0053
- 2026-02-26 - APPROVED Pedestrian Level Wind Study - D07-12-21-0053
- 2026-02-26 - APPROVED Noise Impact Study Addendum - D07-12-21-0053
- 2026-02-26 - APPROVED Noise Impact Study - D07-12-21-0053
- 2026-02-26 - APPROVED Master Site Plan - D07-12-21-0053
- 2026-02-26 - APPROVED Master Plan Phase 1 - D07-12-21-0053
- 2026-02-26 - APPROVED Landscape Site Plan - D07-12-21-0053
- 2026-02-26 - APPROVED Landscape Plans & Details - D07-12-21-0053
- 2026-02-26 - APPROVED Landscape Plan Phase 1 - D07-12-21-0053
- 2026-02-26 - APPROVED Hydrogeology Assessment - D07-12-21-0053
- 2026-02-26 - APPROVED Geotechnical Investigation - D07-12-21-0053
- 2026-02-26 - APPROVED Elevations West & South - D07-12-21-0053
- 2026-02-26 - APPROVED Elevations East & North - D07-12-21-0053
- 2026-02-26 - APPROVED Construction Impact Assessment Report - D07-12-21-0053
- 2026-02-26 - APPROVED Civil Package - D07-12-21-0053
Added 1 document
Added 1 document
Added 1 document
Added 9 documents
- 2024-11-27 - TIA Update Memo - D07-12-21-0053
- 2024-11-27 - Storm Water Management Report - D07-12-21-0053
- 2024-11-27 - Site Statistics - D07-12-21-0053
- 2024-11-27 - Servicing Report - D07-12-21-0053
- 2024-11-27 - Noise Study Addendum - D07-12-21-0053
- 2024-11-27 - MUP Retaining Wall Design - D07-12-21-0053
- 2024-11-27 - Landscape Drawing Package - D07-12-21-0053
- 2024-11-27 - Civil Drawing Package - D07-12-21-0053
- 2024-11-27 - Architectural Package - D07-12-21-0053
Added 9 documents
- 2024-10-01 - Transportation Impact Assessment - D07-12-21-0053
- 2024-10-01 - SWM Report - D07-12-21-0053
- 2024-10-01 - Site Plan - D07-12-21-0053
- 2024-10-01 - Servicing Report - D07-12-21-0053
- 2024-10-01 - P1 Garage Parking Plan - D07-12-21-0053
- 2024-10-01 - Landscape Plan - D07-12-21-0053
- 2024-10-01 - Hydrogeology Assessment - D07-12-21-0053
- 2024-10-01 - Geotechnical Investigation - D07-12-21-0053
- 2024-10-01 - Civil Drawings - D07-12-21-0053
Added description, height, 43 images and 5 documents
- Status: File Pending (Application File Pending)
- Site redevelopment, preserving Standard Bread Building and including: Retail, Office, Residential (3 towers at 35, 33, and 30 storeys); Und…
- Height: 100.835 m
- Storeys: 1 storey
- 17 renders
- 6 site plans
- 2021-04-26 - Planning Rationale and Design Brief - D07-12-21-0053
- 2021-04-26 - Renderings - D07-12-21-0053
- 2022-03-14 - Floor Plans - D07-12-21-0053
- 2022-03-14 - Renderings - D07-12-21-0053
- 2024-04-22 - Site and Floor Plans - D07-12-21-0053
Site Plans, Elevations and Floor Plans#
Additional Information#
| Date Initiated | 2021-04-26 |
| Ward | Ward 15 - Jeff Leiper |