Summary#

The development proposed are Phase 3 and Phase 4 of The Ottawa Hospital Master Site Plan: Phase 3 is the CUP (Central Utility Plant containing electrical, heating, and cooling equipment, located at the rear of the hospital - Phase 4 is the hospital main building consists of 2-storey podium, two towers (8-12 storey) and pavilion flanking main entrance)

Status
Inactive (Zoning By-law in Effect)

Building Scale (Max.) Based on elevation drawings. Values may be approximate. See sources for exact figures.
Low-rise · 1 storey Data Quality Note Text was extracted using optical character recognition. This may introduce artifacts or misreads. · 7.3 m Data Quality Note Height was partially estimated using visual scale. This may be approximate. Data Quality Note Text was extracted using optical character recognition. This may introduce artifacts or misreads.

Additional Information#

Date Initiated2022-12-09

Documents#

TypeDocument
Architectural Plans2020-08-12 - Approved Site Plan & Details Pad B - D07-12-19-0168
Architectural Plans2020-08-12 - Approved Site Plan & Details CRU-B2 and D - D07-12-19-0168
Architectural Plans2020-08-12 - Approved Sediment & Erosion Control Plan - D07-12-19-0168
Architectural Plans2020-08-12 - Approved Ponding Plan - D07-12-19-0168
Architectural Plans2020-08-12 - Approved Pad B Plans & Elevations - D07-12-19-0168
Architectural Plans2020-08-12 - Approved Pad B Landscape Plan - D07-12-19-0168
Architectural Plans2020-08-12 - Approved Overall Landscape Plan - D07-12-19-0168
Architectural Plans2020-08-12 - Approved Master Plan - D07-12-19-0168
Architectural Plans2020-08-12 - Approved ICD Plan - D07-12-19-0168
Architectural Plans2020-08-12 - Approved General Plan of Services - D07-12-19-0168
Architectural Plans2020-08-12 - Approved CRU-2a & Box D Landscape Plan - D07-12-19-0168
Architectural Plans2020-08-12 - Approved CRU B-2a Expansion Plans - D07-12-19-0168
Architectural Plans2020-08-12 - Approved CRU B-2a Expansion Elevations - D07-12-19-0168
Architectural Plans2020-08-12 - Approved Box D Plans - D07-12-19-0168
Architectural Plans2020-08-12 - Approved Box D Elevations - D07-12-19-0168
Architectural Plans2020-03-30 - Engineering Plans - D07-12-19-0168
Architectural Plans2020-03-30 - Architectural Drawings Set - D07-12-19-0168
Architectural Plans2020-01-21 - Site Plan - D07-12-19-0168
Architectural Plans2020-01-21 - Sediment & Erosion Control Plan - D07-12-19-0168
Architectural Plans2020-01-21 - Pad B Plans & Elevations - D07-12-19-0168
Architectural Plans2020-01-21 - Pad B Landscape Plan - D07-12-19-0168
Architectural Plans2020-01-21 - Overall Landscape Plan - D07-12-19-0168
Architectural Plans2020-01-21 - General Plan of Services - D07-12-19-0168
Architectural Plans2020-01-21 - CRU B-2a Elevations - D07-12-19-0168
Architectural Plans2020-01-21 - CRU B-2a & Box D Landscape Plan - D07-12-19-0168
Architectural Plans2020-01-21 - CRU B-2a Plans - D07-12-19-0168
Architectural Plans2020-01-21 - Box D Plans - D07-12-19-0168
Architectural Plans2020-01-21 - Box D Elevations - D07-12-19-0168
Architectural Plans2019-10-22 -CRU Expansion Elevations - D07-12-19-0168
Architectural Plans2019-10-22 - Site Plan Details - D07-12-19-0168
Architectural Plans2019-10-22 - Site Plan - D07-12-19-0168
Architectural Plans2019-10-22 - Planting Plan - D07-12-19-0168
Architectural Plans2019-10-22 - Pad B - Plans & Elevations - D07-12-19-0168
Architectural Plans2019-10-22 - Eng Plans - D07-12-19-0168
Architectural Plans2019-10-22 - CRU Expansion Plans - D07-12-19-0168
Architectural Plans2019-10-22 - Box D Plans - D07-12-19-0168
Architectural Plans2019-10-22 - Box D Elevations - D07-12-19-0168
Electrical Plan2020-01-21 - Lighting Plan - D07-12-19-0168
Electrical Plan2019-10-22 - Site Lighting Plan - D07-12-19-0168
Environmental2020-08-12 - Approved Phase I ESA Update - D07-12-19-0168
Environmental2019-10-22 - Phase I ESA Update - D07-12-19-0168
Environmental2019-10-22 - ESA Affidavit CRU & Pad - D07-12-19-0168
Geotechnical Report2020-08-12 - Approved Grading Plan - D07-12-19-0168
Geotechnical Report2020-08-12 - Approved Geotechnical Investigation - D07-12-19-0168
Geotechnical Report2020-01-21 - Grading Plan - D07-12-19-0168
Landscape Plan2020-03-30 - Landscape Plan - D07-12-19-0168
Noise Study2020-08-12 - Approved Noise Study - D07-12-19-0168
Noise Study2019-10-22 - Noise Study - D07-12-19-0168
Planning2019-10-22 - Planning Rationale - D07-12-19-0168
Site Servicing2020-08-12 - Approved Site Servicing Brief - D07-12-19-0168
Site Servicing2020-03-30 - Site Servicing Brief - D07-12-19-0168
Site Servicing2020-01-21 - Site Servicing Brief - D07-12-19-0168
Site Servicing2019-10-22 - Site Servicing Brief - D07-12-19-0168
Stormwater Management2020-08-12 - Approved Storm Tributary Areas - D07-12-19-0168
Surveying2019-10-22 - Survey - D07-12-19-0168.pdf
Transportation Analysis2020-08-12 - Approved Transportation Impact Assessment - D07-12-19-0168
Transportation Analysis2020-01-21 - TIA Report - D07-12-19-0168
Transportation Analysis2019-10-22 - TIA Report - D07-12-19-0168
2020-08-12 - Signed Delegated Authority Report - D07-12-19-0168
2020-08-12 - Approved Schedules & Notes - D07-12-19-0168
2020-08-12 - Approved Sanitary Tributary Areas - D07-12-19-0168
2020-01-21 - Schedules & Notes - D07-12-19-0168
2020-01-21 - Pad B Site Details - D07-12-19-0168
2020-01-21 - CRU-B2 & D Site Details - D07-12-19-0168
2019-10-22 - Original Phase I ESA - D07-12-19-0168
2019-10-22 - Geotech - D07-12-19-0168