Ottawa Development Projects

1495 Heron Rd.#

Last updated: 2026-09-04 · ID: D02-02-26-0064

Summary#

The proposal involves rezoning lands from Institutional (INZ) and Mainstreet Corridor (CM2) to Neighbourhood Mixed Use (NMU[2990]) Zone, along with amendments to site-specific provisions and the removal of a Holding Symbol. This development is projected to accommodate a total population of 2,098 persons and feature 1.3 ha of commercial/institutional area.

Status
Active (Comment Period in Progress)
Project Type
Zoning By-law Amendment
Property Type
Commercial
Institutional

Location#

Select a marker to view the address.

Project Updates#

2026-09-01 Documents
Added description and 2 documents
  • Updated description:The proposal involves rezoning lands from Institutional (INZ) and Mainstreet Corridor (CM2) to Neighbourhood Mixed Use (NMU[2990]) Zone, al…
2026-08-28 Status
Status Updated
  • Status: Active (Comment Period in Progress)
2026-08-26 Initial Update
Added description and 13 documents
  • Status: Active (Community Heads Up - supporting documents to be posted later during circulation period)
  • The City of Ottawa is proposing a rezoning of lands from Institutional (INZ) and Mainstreet Corridor (CM2) to Neighbourhood Mixed Use (NMU[…

Additional Information#

Date Initiated2026-08-05
WardWard 18 - Marty Carr

Documents#

TypeDocument
Application Summary2026-08-26 - Application Summary - D02-02-26-0064
Architectural Plans2026-08-26 - Conceptual Site Plan - D02-02-26-0064
Architectural Plans2026-08-26 - Conceptual Grade Control Plan - D02-02-26-0064
Architectural Plans2026-09-03 - Concept Plan - D02-02-26-0064
Existing Conditions2026-08-26 - Existing Conditions Plan - D02-02-26-0064
Planning2026-08-26 - Zoning Memo - D02-02-26-0064
Site Servicing2026-08-26 - Functional Servicing Report - D02-02-26-0064
Site Servicing2026-08-26 - Conceptual Overall Servicing - D02-02-26-0064
Site Servicing2026-08-31 - Functional Servicing & Stormwater Mangement Report - D02-02-26-0064
Stormwater Management2026-08-26 - Existing Storm Drainage Plan - D02-02-26-0064
Stormwater Management2026-08-26 - Conceptual Storm Sewer System - D02-02-26-0064
2026-08-26 - Parkland Memo - D02-02-26-0064
2026-08-26 - Heritage Impact Assessment - D02-02-26-0064
2026-08-26 - Conceptual Watermain System - D02-02-26-0064
2026-08-26 - Conceptual Sanitary Sewer System - D02-02-26-0064
2026-08-31 - Drawing Set - D02-02-26-0064